Pinga/ Cajarina Intersection Upgrade

Client
Town Of Port Hedland
Location
Port Hedland
Commencement
December 2012
Completion
January 2013
Value
(undisclosed)
Scope of Works
Construction of earthworks, road works and drainage at the Pinga Street/Cajarina Road intersection.
Construction Activities
- Removal and disposal of vegetation, disposal of debris and other deleterious material
- Excavating, placing and compaction of fill to back of kerb height
- Setting out and construction of roads, footpaths, kerbs, pavement repair, erection of street signs and installation of line marking
- Setting out and construction of open drains
- Clean and repair existing on road drainage and storm water drains
- Full reinstatement of the site
- Provision of "As Constructed" plans for submission to the Local Authority for roads and drainage
Achievements
Extensive traffic management planning, implementation and advanced notification resulted in minimal disruption to road users and street side vendors.